A running log of construction progress for the Library Renovation Project. Check back here for the latest news, or return to the project overview.
Latest updates
- July 8, 2026: Some library services are still temporarily unavailable. Patrons can use printing services in Room 112 of the Library Annex.
- July 7, 2026: Drywall partitions go up on the first and second floors. Library services will be temporarily unavailable. The building will remain open.
- July 6, 2026: Construction begins. Study rooms close and first floor services relocate to the second floor.